| 140 Kb jpg picture Morehead Lake Hydro Project - Site A Powerhouse General Arrangement - Section. | 32 Kw Output 315mm Kaplan Turbine 75 Hp 3 Phase Induction Genarator |
![]() | ![]() |
| 124 Kb jpg picture Morehead Lake Hydro Project - Site A Electrical One-Line Diagram | Electrical Panel Induction Generator Interties |
| Side View of Aluminium intake box with stainless steel screen cover 33 Kb |
| 1. Penstock (330' of 24" 1/4" wall pipe) | $8,200.00 |
| 2. Penstock construction (labor and materials) | $4,300.00 |
| 3. Valves, flanges, reducers, couplers & miscelaneous | $4,000.00 |
| 4. Intake screen | $5,000.00 |
| 5. Powerhouse excavation cement rebar & building) | $12,000.00 |
| 6. Labour (cement works) | $6,000.00 |
| 7. Turbine (1 315mm Kaplan turbine) | $20,500.00 |
| 8. Generator, panel, transformer & electrical | $20,800.00 |
| 9. Powerline (3 spans) | $2,500.00 |
| 10. Engineering, consultation & commissioning | $9,000.00 |
| 11. Total completed project | $92,300.00 |
| Head | 8.2 Meters (27 feet) |
| Flow | .5 M3/s (17.7 cfs) |
| Penstock size | 61 cm (24 inches) |
| Penstock length | 107 Meters (330 feet) |
| Dam Type | Earth and Stoplog |
| Dam heigth | 8.2 Meters (27 feet) |
| Kilowatts produced at maximum flow | 32 Kw |
| Watershed size | 66 Square Km (25.5 sq miles) |
| Price per Installed Kilowatt | $2,884.00 |
![]() |
![]() |
| 136 Kb jpg picture Waterfall - Plan View of Powerhouse |
Penstock Manifold at Powerhouse Final Weld |
| 1. Penstock (230' of 30" 3/8" wall pipe) | $10,000.00 |
| 2. Penstock construction (labor and materials) | $7,000.00 |
| 3. Valves, flanges, reducers, couplers & miscelaneous | $6,000.00 |
| 4. Dam & Intake (excavation, cement, rebar) | $12,000.00 |
| 5. Powerhouse excavation cement rebar & building) | $20,000.00 |
| 6. Labour (cement works, dam, powerhouse & thrust blocks) | $6,000.00 |
| 7. Pumps (1 6x8, 1 8x10, 1 8x10) | $12,400.00 |
| 8. 3 Generators & panel control for pumps | $35,800.00 |
| 9. Transformer & Electrical | $8,000.00 |
| 10. Engineering, consultation & commissioning | $12,000.00 |
| 11. Turbine (1 315mm Kaplan turbine) | $20,500.00 |
| 12. 1 150Hp 3 Phase Induction generator | $9,000.00 |
| 13. 100 Kw Panel & protection | $15,000.00 |
| 14. Powerline (14 spans) | $15,000.00 |
| 15. Access, stairway & walkways | $7,000.00 |
| 16. Testing switchgear, panel & load dumps | $14,000.00 |
| 17. Total completed project | $209,700.00 |
| Head | 17 Meters (56 feet) |
| Flow | .75 M3/s (27.7 cfs) |
| Penstock size | 76 cm (30 inches) |
| Penstock length | 74 Meters (230 feet) |
| Dam Type | Concrete and Stoplog |
| Dam heigth | 2.4 Meters (7 feet) |
| Kilowatts produced at maximum flow | 100 Kw |
| Watershed size | 90 Square Km (35.5 sq miles) |
| Price per Installed Kilowatt | $2,097.00 |